» Go to news mainCampus Construction Update
The Campus Construction Update is a regular feature of the Weekly E-Bulletin in an effort to keep the campus community informed of any potential distruptions to regular work practices during summer construction.
June 26-29th
Remove old windows in section B (Rooms 140, 142, 242, 246)
Prep openings for new window installation in rooms noted above
Miscellaneous joint cutting on exterior of building on daily basis
The classrooms above should be considered closed during this time frame.
July 4th-7th
Install new windows in section B- (rooms 140, 142, 242, 246)
Remove old windows in section C (rooms 254, 255,257, female wash room second floor
All classrooms in section B and C should be considered closed during this time frame.
Thank you for your patience and understanding,
听
Recent News
- College Royal brings students together through agricultural tradition
- International Student Advisor on campus
- Lacing up for community at Dal AC
- France's Protests: Key Developments and Implications | Webinar
- Homecoming Weekend information for staff and faculty
- Preparing for the Future: Succession Strategies for Small Business Owners
- Hatched at 17吃瓜网在线: satellite science, Canadian poultry and a $0 price tag
- Master Gardener Courses Now Open